PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

NEC Capital Solutions, Ltd.

NECキャピタルソリューション株式会社

Offtaker:

NEC Platforms, Ltd.

NECプラットフォームズ株式会社

Industry:

Electrical Manufacturing

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

1.158MW (DC)

Inverter:

-

Generation:

1.396GWh/year

Status and timeline

Status:

Live

*

Disclosed:

July 29, 2021

COD:

2021/08 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • NEC Capital Solutions developed rooftop solar power plants on six buildings including the factory building within NEC Platforms’ Kofu Branch’s premises
  • The generated power is expected to account for approximately 14% of the branch’s consumption
  • NEC Facilities was in charge of the project’s EPC

Image(s)

NEC Capital Solutions, Ltd.'s other PPAs

NEC Platforms, Ltd.'s other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.