PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Undisclosed

未公開

Offtaker:

Sapporo Breweries Limited

サッポロビール株式会社

Industry:

F&B Manufacturing

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

0.627GWh/year

Status and timeline

Status:

Live

*

Disclosed:

January 20, 2022

COD:

2022/03 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • An undisclosed generator developed a solar power plant at Sapporo Breweries’ Gunma (Ojima) Factory in Ota City, Gunma Prefecture
  • The 1,072 panels cover an area of 2,500 square meters and are expected to result in an 330-ton per year CO2 emission reduction