PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

GRE Bihoku Co., Ltd.

合同会社GRE備北

Offtaker:

Niimi City

新見市

Industry:

Municipality

Capacity and generation

T&D area:

Chugoku

Technology:

Solar

Capacity:

0.33715MW (DC)

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

March 8, 2023

COD:

2023/03

Duration:

20

Additional details

  • GRE Bihoku, a joint venture between The San-in Godo Bank and Gatt, developed a solar power plant at Niimi University in Niimi City, Okayama Prefecture