PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Kokuho System Co., Ltd.

株式会社コクホーシステム

Offtaker:

Fujisawa City

藤沢市

Industry:

Municipality

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

0.311MW (DC)

Inverter:

-

Generation:

0.356GWh/year

Status and timeline

Status:

Live

*

Disclosed:

March 20, 2023

COD:

2024/04 (expected)

Duration:

20

* Presumed live based on the expected COD.

Additional details

  • Kokuho System was selected as the winner of Fujisawa City’s FY2023 tender for power supply via a PPA
  • As part of the PPA, Kokuho System will develop four new solar power plants at the city’s facilities including Fujisawa City Honmachi Elementary School, Daiichi Junior High School, Rokuai Junior High School, and Asahicho Parking Lot
  • Excess power will be stored and used at a later time using batteries

Kokuho System Co., Ltd.'s other PPAs

Fujisawa City's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.