PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Sustech, Inc.

株式会社Sustech

Offtaker:

Daisei Warehousing & Transportation Co., Ltd.

ダイセー倉庫運輸株式会社

Industry:

Logistics

Capacity and generation

T&D area:

Chubu

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

2.21GWh/year

Status and timeline

Status:

Upcoming

Disclosed:

March 29, 2023

COD:

2025/07 (expected)

Duration:

Undisclosed

Additional details

  • Sustech will develop a solar power plant at Daisei Warehousing & Transportation’s Komaki No. 3 Logistics Center which is expected to finish construction in July 2025
  • The generation from this PPA is expected to account for approximately 56% of the logistics center’s consumption

Sustech, Inc.'s other PPAs