PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

NTT Anode Energy Corporation

NTTアノードエナジー株式会社

Offtaker:

NEC Platforms, Ltd.

NECプラットフォームズ株式会社

Industry:

Electrical Manufacturing

Capacity and generation

T&D area:

Tohoku

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

*

Disclosed:

April 6, 2023

COD:

June 1, 2024 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • NTT Anode Energy developed solar power plants from which it will deliver power to NEC Platforms’ Fukushima Branch
  • This PPA is part of a wider cooperation on sustainability announced by the two companies in April 2023
  • NEC Platforms manufactures components for NTT’s 5G base stations among other things

NTT Anode Energy Corporation's other PPAs

NEC Platforms, Ltd.'s other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.