PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TESS Engineering Co., Ltd.

テス・エンジニアリング株式会社

Offtaker:

Imuraya

井村屋株式会社

Industry:

F&B Manufacturing

Capacity and generation

T&D area:

Kansai

Technology:

Solar

Capacity:

0.66816MW (DC)

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

April 10, 2023

COD:

2023/03

Duration:

Undisclosed

Additional details

  • TESS Engineering installed 1,152 580W Hanwha Q CELLS panels on Imuraya Anotsu Factory’s rooftop in Tsu City, Mie Prefecture
  • It also installed a 1,000kWh/300kW Huawei storage battery

Image(s)