PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TESS Engineering Co., Ltd.

テス・エンジニアリング株式会社

Offtaker:

DMG Mori Seiki

DMG森精機株式会社

Industry:

Machinery

Capacity and generation

T&D area:

Kansai

Technology:

Solar

Capacity:

13.4MW (DC)

Inverter:

-

Generation:

14GWh/year

Status and timeline

Status:

Partially live

Disclosed:

April 10, 2023

COD:

2023/02 - 2025/01 (expected)

Duration:

Undisclosed

Additional details

  • TESS Engineering commissioned 9,042 590W and 192 455W Toyo Aluminum panels (5,422.14kW total) at DMG Mori Iga Campus in Iga City, Mie Prefecture, in February 2023
  • In March 2024, the PPA’s second phase commissioned, adding 5.2MW of capacity
  • The third phase is expected to commission in January 2025, adding the remaining 2.8MW
  • Once fully operational, the PPA is expected to account for approximately 30% of Iga Campus’s consumption

Image(s)

TESS Engineering Co., Ltd.'s other PPAs

DMG Mori Seiki's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.