PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Undisclosed

未公開

Offtaker:

Sapporo Breweries Limited

サッポロビール株式会社

Industry:

F&B Manufacturing

Capacity and generation

T&D area:

Chugoku

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

0.407GWh/year

Status and timeline

Status:

Live

Disclosed:

July 3, 2023

COD:

July 1, 2023

Duration:

Undisclosed

Additional details

  • An undisclosed generator developed a solar power plant at Sapporo Breweries’ Okayama Winery in Akaiwa City, Okayama Prefecture
  • The 696 panels cover an area of 1,796 square meters and are expected to result in a 222-ton per year CO2 emission reduction
  • This is Sapporo Breweries’ third on-site PPA after one at its Gunma Factory and one at its Hokkaido Factory

Image(s)

Undisclosed's other PPAs

Sapporo Breweries Limited's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.