PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Sustainable Energy K.K.

サステナブルエネルギー合同会社

Retailer:

TEPCO Energy Partner

東京電力エナジーパートナー株式会社

Offtaker:

Chuo-Nittochi Group

中央日本土地建物株式会社

Industry:

Real Estate

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

0.4712MW (DC)

Inverter:

0.4MW (AC)

Generation:

0.54GWh/year

Status and timeline

Status:

Live

*

Disclosed:

July 5, 2023

COD:

2023/11 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • The partnership, which is part of PHOTON CAPITAL, will build a solar power plant dedicated to this PPA in Fukaya City, Saitama Prefecture
  • The generated power will be supplied to both the tenants’ and public portions of three buildings owned by the Chuo-Nittochi Group: Nittochi Building (Chiyoda City, Tokyo), Nittochi Nihonbashi East Building (Chuo City, Tokyo), and Nittochi Okachimachi Building (Taito City, Tokyo)
  • Combined with additionally purchased renewable energy credits, 100% of the buildings’ power consumption is expected to become renewable

Sustainable Energy K.K.'s other PPAs

Chuo-Nittochi Group's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.