PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Kyushu Electric Power Co., Inc.

九州電力株式会社

Offtaker:

Izumi Co., Ltd.

株式会社イズミ

Industry:

Retail

Capacity and generation

T&D area:

Kyushu

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

July 18, 2023

COD:

July 29, 2023

Duration:

Undisclosed

Additional details

  • Kyushu EPCO developed a solar power at Izumi’s youme Mall Iizuka in Iizuka City, Fukuoka Prefecture
  • Izumi will also purchase renewable energy credits from Kyushu EPCO to cover the remaining portion of the facility’s power consumption