PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Harebare G.K.

合同会社HARE晴れ

Retailer:

Hokkaido Electric Power Co., Inc.

北海道電力株式会社

Offtaker:

Aeon Hokkaido

イオン北海道株式会社

Industry:

Retail

Capacity and generation

T&D area:

Hokkaido

Technology:

Solar

Capacity:

12MW (DC)

Inverter:

-

Generation:

20GWh/year

Status and timeline

Status:

Live

*

Disclosed:

August 4, 2023

COD:

January 31, 2024 - 2025/03 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • Aeon Hokkaido will use the procured power at ten of its stores in Hokkaido
  • Harebare will build six 2 MW DC solar power plants, the first of which was put into service in Kita-Hiroshima on January 31, 2024
  • Harebare is a joint venture between Hokkaido EPCO and ARC Co., Ltd. established on July 21, 2023
  • According to Hokkaido EPCo, this is one of the largest offsite PPA projects in Hokkaido

Image(s)

Harebare G.K.'s other PPAs

Aeon Hokkaido's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.