PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Gogin Energy Co., Ltd.

ごうぎんエナジー株式会社

Offtaker:

Yamadaya Corporation

株式会社ヤマダヤ

Industry:

Retail

Capacity and generation

T&D area:

Chugoku

Technology:

Solar

Capacity:

0.26945MW (DC)

Inverter:

-

Generation:

0.257GWh/year

Status and timeline

Status:

Live

*

Disclosed:

August 31, 2023

COD:

2023/10 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • Gogin Energy will develop a solar power plant at Yamadaya’s Himari Oba store in Matsue City, Shimane Prefecture
  • The generated power is expected to account for approximately 21.5% of the facility’s consumption

Gogin Energy Co., Ltd.'s other PPAs

Yamadaya Corporation's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.