PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Harebare G.K.

合同会社HARE晴れ

Retailer:

Hokkaido Electric Power Co., Inc.

北海道電力株式会社

Offtaker:

Sapporo Toyota

札幌トヨタ自動車株式会社

Industry:

Automotive

Capacity and generation

T&D area:

Hokkaido

Technology:

Solar

Capacity:

0.4MW (DC)

Inverter:

-

Generation:

0.5GWh/year

Status and timeline

Status:

Upcoming

Disclosed:

September 29, 2023

COD:

FY2024 (expected)

Duration:

Undisclosed

Additional details

  • Harebare, a joint venture between Hokkaido EPCO and Arc, will supply power from its solar plant in Kita Hiroshima City, Hokkaido, to Sapporo Toyota’s 33 dealerships and 2 other facilities operated
  • The PPA is expected to account for about 12% of the 35 facilities’ power consumption