As part of this PPA, Mori Building in cooperation with Ecokaku will, between FY2023 end and FY2024, develop six agrisolar power plants covering an area of approximately 10ha; grain, soybeans, and other crops will be grown at the power plants
The power plants will be located in Kuwayama (Chikusei City, Ibaraki Prefecture), Niisatocho (Kiryu City, Gunma Prefecture), Miyamachi (Tochigi City, Tochigi Prefecture), Gongendo (Satte City, Saitama Prefecture, two power plants), and Senzuka (Satte City, Saitama Prefecture)
The power will be supplied to Toranomon Hills Mori Tower and other “Hills” buildings operated by Mori
On February 13, 2024, “Mori Building Chikusei City Kuwayama Agricultural Solar Power Plant” became the first power plant to commence commercial operations as part of this PPA; the plant will generate approximately 0.280GWh/year, and the power will be supplied to Toranomon Hills Mori Tower
Once fully operational, the PPA is expected to cover approximately 10% to 15% of each Hills buildings’ consumption
Image(s)
Mori Building Co., Ltd.'s other PPAs
Disclosed
Offtaker
Model
MW DC
Mori Building Co., Ltd.'s other PPAs
Start typing and press enter to search
Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.
Submit the form below to receive a sample issue of The Japan Power Industry Executive.