PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Hakuto Co.,Ltd.

伯東株式会社

Offtaker:

San Ei Giken Inc.

サンエー技研株式会社

Industry:

Electrical Manufacturing

Capacity and generation

T&D area:

Kansai

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

*

Disclosed:

November 10, 2023

COD:

2024/04 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • Hakuto will develop a solar power plant on San Ei Giken’s rooftop in Amagasaki City, Hyogo Prefecture