PPA overview

Contract model and parties

Model:

Virtual

Generator:

Mitsubishi Corporation Clean Energy Ltd.

三菱商事クリーンエナジー株式会社

Offtaker:

Mitsubishi Estate

三菱地所株式会社

Industry:

Real Estate

Capacity and generation

T&D area:

-

Technology:

Solar

Capacity:

3MW (DC)

Inverter:

3MW (AC)

Generation:

4.1GWh/year

Status and timeline

Status:

Live

*

Disclosed:

November 15, 2023

COD:

FY2024 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • Mitsubishi Clean Energy will build a number of solar power plant from which renewable energy credits will be sold directly to Mitsubishi Estate

Mitsubishi Corporation Clean Energy Ltd.'s other PPAs

Mitsubishi Estate's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.