PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Techno Yazaki Co., Ltd.

テクノ矢崎株式会社

Offtaker:

Yazaki Energy Systems Co., Ltd.

⽮崎エナジーシステム株式会社

Industry:

Electrical Manufacturing

Capacity and generation

T&D area:

Chubu

Technology:

Solar

Capacity:

1MW (DC)

Inverter:

-

Generation:

0.88GWh/year

Status and timeline

Status:

Live

Disclosed:

December 12, 2023

COD:

2024/03

Duration:

Undisclosed

Additional details

  • Techno Yazaki built a solar power plant at its subsidiary’s Yazaki Energy System’s Hamamatsu Factory in Hamamatsu City, Shizuoka Prefecture
  • The companies plan to supply excess power to Yazaki Energy System’s Tenryu Factory in Hamamamatsu City, Shizuoka Prefecture, through self-wheeling
  • The PPA will account for approximately 48% of Hamamatsu Factory’s consumption
  • The PPA is expected to lead to approximately 530t-CO2/year emission reduction

Techno Yazaki Co., Ltd.'s other PPAs

Yazaki Energy Systems Co., Ltd.'s other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.