PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

ITOCHU ENEX Co., Ltd.

伊藤忠エネクス株式会社

Offtaker:

I-NET Corporation

株式会社アイネット

Industry:

Information Technology

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

February 6, 2024

COD:

January 1, 2024

Duration:

Undisclosed

Additional details

  • The power will be generated at ITOCHU’s i Missions Park Nasu and i Missions Park Yoshikawa Minami logistics facilities and supplied to I-NET’s Data Center I
  • This PPA is expected to cover about 20% of the data center’s power consumption