PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Tokyu Corporation-Mitsubishi HC Capital JV

東急株式会社・三菱HCキャピタルエナジー株式会社SPC

Retailer:

Tokyu Power Supply Co., Ltd.

株式会社東急パワーサプライ

Offtaker:

Tokyu Corporation

東急株式会社

Industry:

Conglomerate

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

20MW (DC)

Inverter:

-

Generation:

Status and timeline

Status:

Upcoming

Disclosed:

February 8, 2024

COD:

2024/04 - FY2025 (expected)

Duration:

Undisclosed

Additional details

  • The special purpose entity (SPE) aims to develop solar power plants to help Tokyu Corporation achieve “self-production and self-consumption” of renewable power at railways, buildings, hotels, and other facilities
  • The SPE was established by Tokyu Corporation and Mitsubishi HC Capital Energy in June 2023; the latter will develop the assets with the support of Mitsubishi HC Capital

Tokyu Corporation-Mitsubishi HC Capital JV's other PPAs

Tokyu Corporation's other PPAs

Monthly Report - The Japanese Power Industry Executive