PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TEPCO Ventures Co., Ltd.

東京電力ベンチャーズ株式会社

Offtaker:

Proterial, Ltd.

株式会社プロテリアル

Industry:

Metal Manufacturing

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

9.705MW (DC)

Inverter:

-

Generation:

1.15GWh/year

Status and timeline

Status:

Live

Disclosed:

February 15, 2024

COD:

February 1, 2024

Duration:

Undisclosed

Additional details

  • Sharp Energy Solutions served as the EPC for TEPCO Ventures’ solar power plant on the premises of Proterial’s Kumagaya Magnetic Materials Factory/Global Technology Innovation Center in Kumagaya City, Saitama Prefecture
  • The PPA is expected to account for approximately 10% of the facilities’ consumption and result in approximately 5,100t per year CO2 emission reduction

Image(s)

TEPCO Ventures Co., Ltd.'s other PPAs

Proterial, Ltd.'s other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.