PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Daiwa Energy Co., Ltd.

大和エネルギー株式会社

Offtaker:

Tokyo Nohin Daiko Co., Ltd.

東京納品代行株式会社

Industry:

-

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

0.6888MW (DC)

Inverter:

0.499MW (AC)

Generation:

Status and timeline

Status:

Live

Disclosed:

March 18, 2024

COD:

February 27, 2024

Duration:

Undisclosed

Additional details

  • Daiwa Energy built a solar power plant at Tokyo Nohin Daiko’s Narita Fashion Logistics Center I in Tomisato City, Chiba Prefecture
  • Excess power from the power plant will be sold under the FIT scheme
  • Construction on the plant started on October 14, 2023, and finished the same day the plant commenced commercial operations

Image(s)

Daiwa Energy Co., Ltd.'s other PPAs

Tokyo Nohin Daiko Co., Ltd.'s other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.