PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Hokuriku Electric Power Biz Energy Solution Co., Ltd.

北陸電力ビズ・エナジーソリューション株式会社

Offtaker:

Takaoka City

高岡市

Industry:

Municipality

Capacity and generation

T&D area:

Hokuriku

Technology:

Solar

Capacity:

0.122MW (DC)

Inverter:

-

Generation:

0.122GWh/year

Status and timeline

Status:

Live

*

Disclosed:

March 25, 2024

COD:

July 15, 2024 (expected)

Duration:

20

* Presumed live based on the expected COD.

Additional details

  • Hokuriku EPCO’s subsidiary developed a solar power plant with 296 panels at an unused plot of land next to Takaoka Funeral Hall (Green Park) in Takaoka City, Toyama Prefecture
  • The PPA is expected to cover 10% of the facility’s consumption and reduce CO2 emissions by 54t per year
  • At the end of the contract period, the equipment ownership will be transferred to the city

Image(s)

Hokuriku Electric Power Biz Energy Solution Co., Ltd.'s other PPAs

Takaoka City's other PPAs