PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Daigas Energy Co., Ltd.

Daigasエナジー株式会社

Offtaker:

Toyo Koken K.K.

トーヨーコーケン株式会社

Industry:

Machinery

Capacity and generation

T&D area:

Chubu

Technology:

Solar

Capacity:

0.153MW (DC)

Inverter:

-

Generation:

0.15GWh/year

Status and timeline

Status:

Live

*

Disclosed:

March 26, 2024

COD:

2024/04 (expected)

Duration:

20

* Presumed live based on the expected COD.

Additional details

  • Daigas Energy will develop a solar power plant at Toyo Koken’s Yamanashi branch in Minami Alps City, Yamanashi Prefecture
  • The project is done by Daigas Energy in conjunction with Yamazen as part of their DayZpower joint business

Image(s)

Daigas Energy Co., Ltd.'s other PPAs

Toyo Koken K.K.'s other PPAs