PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TESS Engineering Co., Ltd.

テス・エンジニアリング株式会社

Offtaker:

Nanchiku Co., Ltd.

株式会社ナンチク

Industry:

F&B Manufacturing

Capacity and generation

T&D area:

Kyushu

Technology:

Solar

Capacity:

0.7497MW (DC)

Inverter:

-

Generation:

0.89GWh/year

Status and timeline

Status:

Live

Disclosed:

March 29, 2024

COD:

2024/03

Duration:

20

Additional details

  • TESS Engineering developed a solar power plant on Nanchiku’s headquarters/factory in Soo City, Kagoshima Prefecture
  • The generated power is expected to account for approximately 7.6% of the facility’s consumption
  • Nanchiku aims to expand on-site PPA generation to over 250MW by 2030

Image(s)

TESS Engineering Co., Ltd.'s other PPAs

Nanchiku Co., Ltd.'s other PPAs

Monthly Report - The Japanese Power Industry Executive