Contract model and parties

Model:

Physical (on-site)

Generator:

Undisclosed

未公開

Offtaker:

Tosoh Logistics Corporation

東ソー物流株式会社

Industry:

Logistics

Capacity and generation

T&D area:

Chugoku

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

April 1, 2024

COD:

April 1, 2024

Duration:

Undisclosed

Additional details

  • An undisclosed power generator developed a solar power plant on Tosoh Logistics Rinkai Logistics Center A’s rooftop in Shunan City, Yamaguchi Prefecture; it also installed a storage battery
  • The generated power is expected to result in approximately 220t annual reduction in CO2 emissions and cover approximately 10% of the facility’s consumption