PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TN Cross Corporation

TNクロス株式会社

Offtaker:

Kawasaki City

川崎市

Industry:

Municipality

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

*

Disclosed:

April 25, 2024

COD:

2024/12 (expected)

Duration:

20

* Presumed live based on the expected COD.

Additional details

  • TN Cross will build rooftop solar power plants at six elementary schools in Kawasaki City, Kanagawa Prefecture; it will install storage batteries at some of the schools
  • The capacity will be determined based on a site survey and has not been disclosed at this stage
  • The PPA operator was selected through a public call for proposals from Kawasaki City and will receive the city’s subsidy covering 2/3 of the project costs

TN Cross Corporation's other PPAs

Kawasaki City's other PPAs

Monthly Report - The Japanese Power Industry Executive