PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

SMFL MIRAI Partners Co., Ltd.

SMFLみらいパートナーズ株式会社

Offtaker:

KIOXIA Corporation

キオクシア株式会社

Industry:

Electrical Manufacturing

Capacity and generation

T&D area:

Chubu

Technology:

Solar

Capacity:

3.4MW (DC)

Inverter:

-

Generation:

3.8GWh/year

Status and timeline

Status:

Live

Disclosed:

July 1, 2024

COD:

2024/07/01

Duration:

Undisclosed

Additional details

  • SMFL Mirai Partners developed a rooftop solar power plant at KIOXIA Corporation’s Yokkaichi Factory’s No. 5 Production Building in Yokkaichi City, Mie Prefecture; the generated power is being used at the factory
  • The two companies also commissioned an on-site PPA at the factory’s No. 6 Production Building in 2023; combined, the two PPAs have a capacity of 7.3MW, generate 7.9GWh annually, and reduce CO2 emissions by approximately 3.7t per year

Image(s)

SMFL MIRAI Partners Co., Ltd. 's other PPAs

KIOXIA Corporation's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.