PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Advance Maintenance Co., Ltd.

株式会社アドバンスメンテナンス

Retailer:

TEPCO Energy Partner

東京電力エナジーパートナー株式会社

Offtaker:

AT TOKYO Corporation

株式会社アット東京

Industry:

Information Technology

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

3.634MW (DC)

Inverter:

2.4MW (AC)

Generation:

3.79GWh/year

Status and timeline

Status:

Partially live

Disclosed:

July 18, 2024

COD:

2024/07 and 2024/12 (expected)

Duration:

Undisclosed

Additional details

  • Advance Maintenance will develop three solar power plants from which it will supply power to AT TOKYO’s Data Center No. 3 in Tokyo through TEPCO Energy Partner
  • The solar power plants will be in Tochigi and Ibaraki prefectures:
    • Tochigi I: 1.830 MW (DC)/1.150MW (AC)
    • Tochigi II: 1.153 MW (DC)/0.700MW (AC)
    • Ibaraki: 0.651 MW (DC)/0.550 MW (AC)
  • The deal is expected to account for approximately 10% of the data center’s consumption

Advance Maintenance Co., Ltd.'s other PPAs

AT TOKYO Corporation's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.