PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

manorda Iwate Co., Ltd.

manordaいわて株式会社

Retailer:

Kuji Regional Energy Co., Ltd.

久慈地域エネルギー株式会社

Offtaker:

Retail Customers

小売事業顧客

Industry:

-

Capacity and generation

T&D area:

Tohoku

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

2.17GWh/year

Status and timeline

Status:

Live

*

Disclosed:

July 29, 2024

COD:

2025/01 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • manorda Iwate will develop three solar power plants in Kuji City, Iwate Prefecture and supply the generated power to Kuji Regional Energy, which will retail the power to local municipalities, businesses, households, etc.

manorda Iwate Co., Ltd.'s other PPAs

Retail Customers's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.