PPA overview

Contract model and parties

Model:

Physical (hybrid on-/off-site)

Generator:

Nishimatsu Construction Co., Ltd.

西松建設株式会社

Offtaker:

Multiple

複数

Industry:

-

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

July 31, 2024

COD:

2024/07

Duration:

Undisclosed

Additional details

  • Excess power generated at one of the logistics facilities built by Nishimatsu Construction will be delivered to four student dormitories owned by the company (Hiyoshi International Student Dormitory, Shonan Fujisawa Future Creation Academy Student Dormitory (H Village), Takanawa International Student Dormitory, and NCRe Tamagawa Gakuen)
  • The off-site portion of the PPA is expected to account for about 20% (220MWh/year) of the four dormitories’ consumption and lead to 94t per year CO2 emission reduction
  • Adding the off-site component to the on-site PPA will allow Nishimatsu Construction to use 100% of the generated power

Nishimatsu Construction Co., Ltd.'s other PPAs

Multiple's other PPAs

Monthly Report - The Japanese Power Industry Executive