PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Clean Energy Solutions Co., Ltd.

株式会社クリーンエナジー・ソリューションズ

Offtaker:

Mani, Inc.

マニー株式会社

Industry:

-

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

0.15MW (DC)

Inverter:

-

Generation:

0.15308GWh/year

Status and timeline

Status:

Live

Disclosed:

July 31, 2024

COD:

June 6, 2024

Duration:

Undisclosed

Additional details

  • Clean Energy Solutions will build a solar power plant at Mani’s HQ/Kiyohara Factory in Utsunomiya City, Tochigi Prefecture
  • The PPA is expected to result in 67 tons per year CO2 emission reduction

Image(s)

Clean Energy Solutions Co., Ltd.'s other PPAs

Mani, Inc.'s other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.