PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Clean Energy Solutions Co., Ltd.

株式会社クリーンエナジー・ソリューションズ

Offtaker:

Mani, Inc.

マニー株式会社

Industry:

-

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

0.15MW (DC)

Inverter:

-

Generation:

0.15308GWh/year

Status and timeline

Status:

Live

Disclosed:

July 31, 2024

COD:

June 6, 2024

Duration:

Undisclosed

Additional details

  • Clean Energy Solutions will build a solar power plant at Mani’s HQ/Kiyohara Factory in Utsunomiya City, Tochigi Prefecture
  • The PPA is expected to result in 67 tons per year CO2 emission reduction