PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Daigas Energy Co., Ltd.

Daigasエナジー株式会社

Offtaker:

Sanyo Special Steel Co., Ltd.

山陽特殊製鋼株式会社

Industry:

-

Capacity and generation

T&D area:

Kansai

Technology:

Solar

Capacity:

0.51243MW (DC)

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

August 1, 2024

COD:

July 12, 2024

Duration:

Undisclosed

Additional details

  • Daigas Energy developed a rooftop solar power plant on Sanyo Special Steel’s warehouse in Himeji City, Hyogo Prefecture; it also built a private line to deliver that power from the power plant to Sanyo Special Steel’s factory across the street