Model:

Physical (on-site)

Generator:

Undisclosed

未公開

Offtaker:

Coca-Cola Bottlers Japan Inc.

コカ・コーラ ボトラーズジャパン株式会社

Industry:

F&B Manufacturing

Capacity and generation

T&D area:

Chugoku

Technology:

Solar

Capacity:

0.1925MW (DC)

Inverter:

-

Generation:

0.25GWh/year

Status and timeline

Status:

Live

Disclosed:

September 25, 2024

COD:

2024/09

Duration:

Undisclosed

Additional details

  • An undisclosed PPA provider installed 350 solar panels on Coca-Cola Bottlers Japan’s Hiroshima Factory in Mihara City, Hiroshima Prefecture
  • The PPA is expected to lead to an approximately 110t-CO2/year emission reduction
  • No solar panels were previously installed at the factory