PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Fuji Technical Co., Ltd.

株式会社富士テクニカルコーポレーション

Retailer:

TEPCO Energy Partner

東京電力エナジーパートナー株式会社

Offtaker:

SUBARU Corporation

株式会社SUBARU

Industry:

Automotive

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

4.1MW (DC)

Inverter:

-

Generation:

4.3GWh/year

Status and timeline

Status:

Live

*

Disclosed:

October 25, 2024

COD:

2025/02 (expected)

Duration:

Undisclosed

* Presumed live based on the expected COD.

Additional details

  • FJTEC will supply power from an undisclosed solar power plant to SUBARU’s Tokyo Office through TEPCO Energy Partner; on weekends and other days when the office is closed, the power will be supplied to the company’s Yajima Plant in Gunma Prefecture instead
  • The PPA is expected to account for approximately 14% of Tokyo Office’s consumption and is expected to lead to CO2 emission reduction of 1,600t/year
  • The project won METI’s FY2023 revised budget “consumer-led solar power introduction subsidy”

Fuji Technical Co., Ltd.'s other PPAs

SUBARU Corporation's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.