PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TESS Engineering Co., Ltd.

テス・エンジニアリング株式会社

Offtaker:

ULVAC Inc.

株式会社アルバック

Industry:

Machinery

Capacity and generation

T&D area:

Kyushu

Technology:

Solar

Capacity:

0.825MW (DC)

Inverter:

-

Generation:

0.78GWh/year

Status and timeline

Status:

Upcoming

Disclosed:

November 6, 2024

COD:

2025/02 (expected)

Duration:

20

Additional details

  • TESS Engineering will develop a solar power plant at ULVAC’s Kyushu Factory in Kirishima City, Kagoshima Prefecture
  • The power plant will use 1,320 625W Jinko Solar panels
  • The PPA is expected to lead to 334t-CO2/year emission reduction

Image(s)