PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Smart Solar Corporation

スマートソーラー株式会社

Offtaker:

Kawasaki City

川崎市

Industry:

Municipality

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

1.8MW (DC)

Inverter:

-

Generation:

2.1GWh/year

Status and timeline

Status:

Upcoming

Disclosed:

November 11, 2024

COD:

FY2025 (expected)

Duration:

20

Additional details

  • As part of the PPA, Smart Solar will develop a solar power plant on Kawasaki City Waterworks Bureau’s Iriezaki Water Treatment Center West Treatment Facility’s rooftop
  • The generated power is expected to account for 9% of the center’s consumption and lead to 900t-CO2/year emission reductions