PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TN Cross Corporation

TNクロス株式会社

Offtaker:

Yokohama City

横浜市

Industry:

Municipality

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Upcoming

Disclosed:

November 15, 2024

COD:

2026/03 to FY2027 (expected)

Duration:

20

Additional details

  • TN Cross will develop solar power plants at up to 50 public schools in Yokohama City, Kanagawa Prefecture