PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Undisclosed

未公開

Offtaker:

Suzuki Motor Corporation

スズキ株式会社

Industry:

-

Capacity and generation

T&D area:

Kansai

Technology:

Solar

Capacity:

0.2496MW (DC)

Inverter:

-

Generation:

0.14189GWh/year

Status and timeline

Status:

Live

Disclosed:

November 29, 2024

COD:

2024/11/20

Duration:

Undisclosed

Additional details

  • An undisclosed PPA provider developed a rooftop power plant at Suzuki Parts Center Kobe
  • The generated power is expected to account for approximately 51% of the facility’s consumption and lead to 60t-CO2/year emission reduction

Image(s)

Undisclosed's other PPAs

Suzuki Motor Corporation's other PPAs

Monthly Report - The Japanese Power Industry Executive