PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Harebare G.K.

合同会社HARE晴れ

Retailer:

Hokkaido Electric Power Co., Inc.

北海道電力株式会社

Offtaker:

Hokkaido Railway Company

北海道旅客鉄道株式会社

Industry:

Railway

Capacity and generation

T&D area:

Hokkaido

Technology:

Solar

Capacity:

2.8MW (DC)

Inverter:

-

Generation:

3.8GWh/year

Status and timeline

Status:

Unknown

Disclosed:

December 18, 2024

COD:

Undisclosed

Duration:

Undisclosed

Additional details

  • Harebare will supply power from two of its solar power plants in Kitahiroshima City, Hokkaido, to JR Hokkaido’s New Chitose Airport Station, Otaru Station, etc. via Hokkaido EPCO
  • Hokkaido EPCO will also sell additional renewable energy certificates to JR Hokkaido to cover the portion of New Chitose Airport Station’s and Otaru Station’s consumption not covered by the PPA

Harebare G.K.'s other PPAs

Hokkaido Railway Company's other PPAs

Monthly Report - The Japanese Power Industry Executive