PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Mitsubishi Electric Financial Solutions Co., Ltd.

三菱電機フィナンシャルソリューションズ株式会社

Offtaker:

Kyosai Electric Co., Ltd.

株式会社京才電機製作所

Industry:

Electrical Manufacturing

Capacity and generation

T&D area:

Chubu

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

December 24, 2024

COD:

2024/08

Duration:

Undisclosed

Additional details

  • Mitsubishi Electric Financial Solutions developed a solar power plant at Kyosai Electric’s factory in Tokoname City, Aichi Prefecture
  • Other Mitsubishi Electric group companies were in charge of the power plant’s EPC and are in charge of its O&M