PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

TN Cross Corporation

TNクロス株式会社

Offtaker:

Yokohama City

横浜市

Industry:

Municipality

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Upcoming

Disclosed:

January 15, 2025

COD:

2027/04 to 2028/01 (expected)

Duration:

20

Additional details

  • TN Cross was selected for Yokohama City’s FY2024 public school renewable energy introduction project
  • Between FY2025 and FY2027, it will install solar panels and BESS at 50 schools in the city

TN Cross Corporation's other PPAs

Yokohama City's other PPAs