PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

EDPR Japan Co., Ltd.

EDPR JAPAN株式会社

Offtaker:

Amazon

Amazon

Industry:

Information Technology

Capacity and generation

T&D area:

Tohoku

Technology:

Solar

Capacity:

44MW (DC)

Inverter:

35MW (AC)

Generation:

48GWh/year

Status and timeline

Status:

Upcoming

Disclosed:

January 29, 2025

COD:

Q3 2025

Duration:

20

Additional details

  • Amazon will offtake all power generated at EDPR Japan’s 35MWAC/44MWDC power plant in Fukushima City, Fukushima Prefecture