PPA overview

Contract model and parties

Model:

Physical (hybrid on-/off-site)

Generator:

Chubu Electric Power Miraiz

中部電力ミライズ株式会社

Retailer:

Chubu Electric Power Miraiz

中部電力ミライズ株式会社

Offtaker:

Multiple

複数

Industry:

-

Capacity and generation

T&D area:

Chubu

Technology:

Solar

Capacity:

5MW (DC)

Inverter:

-

Generation:

6GWh/year

Status and timeline

Status:

Upcoming

Disclosed:

January 31, 2025

COD:

2025/05 to 2026 (expected)

Duration:

Undisclosed

Additional details

  • 15 companies in Shizuoka Prefecture will install solar panels on the rooftops of their facilities as part of this project coordinated by Chubu Electric Power Miraiz; excess generation from the facilities will be supplied to other participating facilities
  • Some of the companies will only procure excess power while others will only supply excess power, some will do both:
    • Only procure excess power: Suzuki, Somic Ishikawa, Yamaha Motor, Rohm Hamamatsu
    • Procure and supply excess power: DOWA Metanix, Hamamatsu Photonics, Yamaha
    • Only supply excess power: Aizen, IO Industry, Enshu, Cataler, Kurabe, Koken Kogyo, Koritu, Koyama Seiki
  • The PPA is expected to lead to 2,500t-CO2/year emission reduction

Chubu Electric Power Miraiz's other PPAs

Multiple's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.