PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

MIRARTH Energy Solutions Inc.

MIRARTHエナジーソリューションズ株式会社

Offtaker:

Yamanashi Prefecture

山梨県

Industry:

-

Capacity and generation

T&D area:

Tokyo

Technology:

Solar

Capacity:

0.337MW (DC)

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

January 31, 2025

COD:

2024/10 to 2024/12

Duration:

Undisclosed

Additional details

  • MIRATH Energy Solutions installed solar panels at five of Yamanashi Prefecture’s public facilities:
    • Yamanashi Prefecture General Agricultural Center (60.4kW; 2024/10 COD)
    • Yamanashi Prefecture Fuji Yoshida Police Station (83.5kW; 2024/10 COD)
    • Yamanashi Industrial Technology Junior College Tsuru Campus (40.0kW; 2024/10 COD)
    • Yamanashi Prefecture Kofu Police Station (69.6kW; 2024/11 COD)
    • Kodomo no Kokoro Support Plaza (83.5kW; 2024/12 COD)

Image(s)

MIRARTH Energy Solutions Inc.'s other PPAs

Yamanashi Prefecture's other PPAs

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.