PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Chudenko Corporation

株式会社中電工

Offtaker:

Hiroshima City

広島市

Industry:

-

Capacity and generation

T&D area:

Chugoku

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Unknown

Disclosed:

February 20, 2025

COD:

Undisclosed

Duration:

20

Additional details

  • Chudenko was selected through a public RFP to build a solar power plant at Hiroshima City Western Water Treatment Center

Chudenko Corporation's other PPAs

Hiroshima City's other PPAs