PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

NTT Anode Energy Corporation

NTTアノードエナジー株式会社

Offtaker:

Sendai City

仙台市

Industry:

Municipality

Capacity and generation

T&D area:

Tohoku

Technology:

Solar

Capacity:

0.38827MW (DC)

Inverter:

-

Generation:

Status and timeline

Status:

Live

*

Disclosed:

March 14, 2025

COD:

2025/04/01 (expected)

Duration:

20

* Presumed live based on the expected COD.

Additional details

  • NTT Anode Energy is building solar power plants at:
    • Sendai City Children’s Welfare Center: 113.92kW
    • Hitachi Systems Hall Sendai (Youth Culture Center): 175.23kW
    • Sendai Bank Hall Izumity 21 (Sendai City Izumi Culture Creation Center): 99.12kW
  • The PPA is expected to lead to 180t-CO2/year emission reduction

Image(s)

NTT Anode Energy Corporation's other PPAs

Sendai City's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.