PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Sumitomo Mitsui Construction Co., Ltd.

三井住友建設株式会社

Retailer:

NTT Anode Energy Corporation

NTTアノードエナジー株式会社

Offtaker:

Undisclosed

未公開

Industry:

-

Capacity and generation

T&D area:

Kansai

Technology:

Solar

Capacity:

1.612MW (DC)

Inverter:

1MW (AC)

Generation:

Status and timeline

Status:

Live

*

Disclosed:

April 25, 2025

COD:

2025/05/01 (expected)

Duration:

25

* Presumed live based on the expected COD.

Additional details

  • Sumitomo Mitsui Construction completed the Kato City Floating Solar Power Plant in Hyogo Prefecture on March 31, 2025
  • For 20 of the 25 years, the power plant will also operate under the FIP scheme

Image(s)

Sumitomo Mitsui Construction Co., Ltd.'s other PPAs

Undisclosed's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.