PPA overview

Contract model and parties

Model:

Physical (on-site)

Generator:

Cenergy Co., Ltd.

株式会社シーエナジー

Offtaker:

Meitetsu City Design Co., Ltd.

名鉄都市開発株式会社

Industry:

Real Estate

Capacity and generation

T&D area:

Chubu

Technology:

Solar

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Upcoming

Disclosed:

May 8, 2025

COD:

Around 2027 (expected)

Duration:

Undisclosed

Additional details

  • Cenergy will build a solar power plant on Meitetsu City Design’s logistics facility MCD-LOGI Komaki in Komaki City, Aichi Prefecture; the power will be consumed on site with plan to expand the scheme in the future to supply excess power to Meitetsu Group via Chubu Electric Power Miraiz

Image(s)

Cenergy Co., Ltd.'s other PPAs

Meitetsu City Design Co., Ltd.'s other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.