PPA overview

Contract model and parties

Model:

Physical (off-site)

Generator:

Kyuden Mirai Energy Corporation

九電みらいエナジー株式会社

Retailer:

Undisclosed

未公開

Offtaker:

Kyocera Corporation

京セラ株式会社

Industry:

-

Capacity and generation

T&D area:

Kyushu

Technology:

Geothermal

Capacity:

-

Inverter:

-

Generation:

Status and timeline

Status:

Live

Disclosed:

May 27, 2025

COD:

2025/04/01

Duration:

Undisclosed

Additional details

  • An undisclosed share of the output of four assets including the 110MW Hatchobaru Power Plant, the 30MW Yamagawa Power Plant, the 30MW Ogiri Power Plant, and the 27.5MW Takigami Power Plant is being supplied to Kyocera’s Kagoshima Hayato Factory in Kirishima City, Kagoshima Prefecture, and other facilities

Kyuden Mirai Energy Corporation's other PPAs

Kyocera Corporation's other PPAs

Japan Energy Hub PPA Report

Submit the form to register CPPAs in 2025: Market Overview, Trends and Opportunities report’s “early bird” pricing.

Monthly Report - The Japanese Power Industry Executive

Submit the form below to receive a sample issue of The Japan Power Industry Executive.